PURPOSE
-
To define a procedure for the sampling plan for incoming material, online process stage, and finished stage.
-
SCOPE
-
This SOP applies to all material which is to be tested for quality.
-
REFERENCE(S) & ATTACHMENTS
-
References
- In-house
-
Attachments
- Nil
-
RESPONSIBILITY
-
QC Department Head: To prepare the SOP and its scope.
-
QA Head: To approve the SOP and to ensure implementation.
-
DISTRIBUTION
-
Quality Assurance
-
Quality Control
-
DEFINITION(S) & ABBREVIATION(S)
-
Definitions
- Nil
-
Abbreviations
- Nil
-
PROCEDURE
-
RM Sampling Plan:
-
For Rolls:
-
1 For incoming raw material in roll form, the sampling plan below shall be used. The basic rule considered is √n+1; however, for a number of rolls below 10, another formula is applied.
-
2 Sample size shall be one metre in length, and width as actually supplied.
-
No. of Rolls Sample to Check
1 to 2 1
3 to 4 2
5 to 6 3
7 to 12 4
13 to 20 5
21 to 30 6
31 to 42 7
43 to 56 8
57 to 72 9
73 to 90 10
91 to 100 11
-
For Inks/Adhesive/VMCH/Lacquer/Solvent, etc.:
-
1 For incoming material which comes in containers, one sample per batch shall be taken.
-
2 Sample size shall be approximately 200 ml.
-
On-Line (Production) Sampling Plan:
-
Slitting Stage: One sample per set shall be taken. Total GSM, HSL Coating GSM, visual, and width shall be checked for each and every roll. Sample size shall be about half a metre in length, and width as actual. Layer separation shall be checked per 3 sets.
-
Printing Stage: Each and every output roll shall be sampled and tested for the defined parameters. Sample size shall be one metre in length, and width as actual.
-
Doctoring/Inspection Stage: One sample per set shall be taken. Total GSM, HSL Coating GSM, visual, and width shall be checked for each and every roll, while layer separation shall be checked per 3 sets. Sample size shall be about half a metre in length, and width as actual.
-
-
Finished Material:
- Each batch of finished material shall be checked on a random basis. Two rolls from each batch of finished material shall be checked at the time of dispatch. Checking shall be visual only.
-
REVISION HISTORY
+----------------+----------------+----------------+----------------+----------------+----------------+ | Revision No. | 00 | Effective | | CC No. | | | | | Date | | | | +----------------+----------------+----------------+----------------+----------------+----------------+ | Details of revision: New SOP | +-----------------------------------------------------------------------------------------------------+