Procedure for Release of FG and Pre-dispatch
Inspection
Purpose
- To define a procedure for release of finished goods and pre-dispatch inspection.
Scope
- This SOP applies to all finished goods material which is either ready in stock or being sold to a specific customer.
Reference(S) & Attachments
- References
- In-house
- Attachments: Nil
Responsibility
- QA Department Person:
- To prepare the SOP.
- QA Head
- To ensure the training of the SOP to all concerned personnel involved in implementation of the SOP.
- To ensure the implementation of the SOP after training.
- Department Head / Plant Head
- To approve new or revised SOP.
- To ensure the implementation of the defined system.
Distribution
- Quality Control
- Production
- Warehouse
Definition(S) & Abbreviation(S)
- Definitions
- Finished Goods: Any material which is finally in the stage at which it can be sold to a customer, i.e. it is meeting all the requirements of the customer's specification.
- Abbreviations
- PDI: Pre-dispatch Inspection
- FG: Finished Goods
Inspection
Procedure
- Release of Finished Goods
- Material after the packing process is considered as the finished product.
- Before this process, the product shall be checked for quality parameters in order to ascertain whether the material is conforming to specification or not.
- Before the packing process, each roll undergoes an inspection / rewinding process. At the inspection and rewinding stage, technical parameters are checked by QC.
- After the packing process, QC shall ensure the below checks visually:
- Packing quality should be good.
- There should be two labels on each roll, one on the top & the other inside the core.
- The information on the label should be complete, like spool no., roll no., joints etc.
- The rolls should be kept on a clean pallet and separate from other products.
- Once these checks are OK, the QC person signs on the Material Transfer Slip of Stores and approves the material.
- After this process, material can be transferred to the FG store.
- Pre-Dispatch Inspection
- The daily dispatch plan is decided based on the daily meeting of the Production Head and Dispatch Supervisor as per priority given by the Planning Head.
- Based on the priority, the Dispatch Supervisor shall prepare the packing list of the material which is to be dispatched.
- The QC person performs the below checks visually on the entire material:
- Packing quality should be good.
- The rolls should be kept on a clean pallet and two products should not mix.
- The QC person performs the below checks visually on any two rolls / boxes on a random basis:
- The information written on the label should match with the packing list, i.e. material name, size, customer name, surface, batch no., retest date etc.
- There should be two labels on each roll, one on the top & the other inside the core.
- The information on the label should be complete, like spool no., roll no., joints etc.
Inspection
Once the material conforms to the checks, the QC person shall put the
“Pre-dispatch Inspection done” stamp on the packing list and put a signature.
Revision History
Revision No.
Effective Date
CC No.
Details of revision: New SOP
Inspection
Attachment : Pre-dispatch Inspection Stamp
The “Pre-dispatch Inspection done” stamp is applied on the packing list by the QC person as evidence of completed pre-dispatch inspection.