Procedure for Release of FG and Pre-dispatch

Inspection

Purpose

  • To define a procedure for release of finished goods and pre-dispatch inspection.

Scope

  • This SOP applies to all finished goods material which is either ready in stock or being sold to a specific customer.

Reference(S) & Attachments

  • References
  • In-house
  • Attachments: Nil

Responsibility

  • QA Department Person:
  • To prepare the SOP.
  • QA Head
  • To ensure the training of the SOP to all concerned personnel involved in implementation of the SOP.
  • To ensure the implementation of the SOP after training.
  • Department Head / Plant Head
  • To approve new or revised SOP.
  • To ensure the implementation of the defined system.

Distribution

  • Quality Control
  • Production
  • Warehouse

Definition(S) & Abbreviation(S)

  • Definitions
  • Finished Goods: Any material which is finally in the stage at which it can be sold to a customer, i.e. it is meeting all the requirements of the customer's specification.
  • Abbreviations
  • PDI: Pre-dispatch Inspection
  • FG: Finished Goods

Inspection

Procedure

  • Release of Finished Goods
  • Material after the packing process is considered as the finished product.
  • Before this process, the product shall be checked for quality parameters in order to ascertain whether the material is conforming to specification or not.
  • Before the packing process, each roll undergoes an inspection / rewinding process. At the inspection and rewinding stage, technical parameters are checked by QC.
  • After the packing process, QC shall ensure the below checks visually:
    • Packing quality should be good.
    • There should be two labels on each roll, one on the top & the other inside the core.
    • The information on the label should be complete, like spool no., roll no., joints etc.
    • The rolls should be kept on a clean pallet and separate from other products.
  • Once these checks are OK, the QC person signs on the Material Transfer Slip of Stores and approves the material.
  • After this process, material can be transferred to the FG store.
  • Pre-Dispatch Inspection
  • The daily dispatch plan is decided based on the daily meeting of the Production Head and Dispatch Supervisor as per priority given by the Planning Head.
  • Based on the priority, the Dispatch Supervisor shall prepare the packing list of the material which is to be dispatched.
  • The QC person performs the below checks visually on the entire material:
    • Packing quality should be good.
    • The rolls should be kept on a clean pallet and two products should not mix.
  • The QC person performs the below checks visually on any two rolls / boxes on a random basis:
    • The information written on the label should match with the packing list, i.e. material name, size, customer name, surface, batch no., retest date etc.
    • There should be two labels on each roll, one on the top & the other inside the core.
    • The information on the label should be complete, like spool no., roll no., joints etc.

Inspection

Once the material conforms to the checks, the QC person shall put the

“Pre-dispatch Inspection done” stamp on the packing list and put a signature.

Revision History

Revision No.

Effective Date

CC No.

Details of revision: New SOP

Inspection

Attachment : Pre-dispatch Inspection Stamp

The “Pre-dispatch Inspection done” stamp is applied on the packing list by the QC person as evidence of completed pre-dispatch inspection.