DG Set Operation
PURPOSE
- 1.1 To define a procedure for operation of DG Set.
SCOPE
- 2.1 This SOP applies to Utility section of Engineering department.
REFERENCE(S) & ATTACHMENTS
-
3.1 References
- 3.1.1 In-house
-
3.2 Attachments
-
3.2.1 Attachment- I : DG Set Log Sheet SIPL/ENI/001/F01/00
-
3.2.2 Attachment- II : PM Check List SIPL/ENI/001/F02/00
-
RESPONSIBILITY
-
4.1 Engineering Department Person:
-
4.1.1 To prepare the SOP.
-
4.1.2 To prepare a list of the SOP in Engineering Department.
-
-
4.2 Engineering Head:
-
4.2.1 To ensure the training of the SOP to all concerned personnel involved in implementation of the SOP.
-
4.2.2 To ensure the implementation of the SOP after training.
-
-
4.3 Quality Assurance Person:
-
4.3.1 To check the SOP.
-
4.3.2 To maintain the original copy of the SOP.
-
4.3.3 To issue controlled copy of the SOP.
-
4.3.4 To maintain issuance record of SOP.
-
4.3.5 To retrieve the controlled copy of the SOP when it is superseded/obsolete and maintain its record.
-
-
4.4 QA Head:
-
4.4.1 To approve new or revised SOP.
-
4.4.2 To ensure the implementation of the defined system.
-
-
4.5 Plant Head:
-
4.5.1 To approve new or revised SOP.
-
4.5.2 To ensure the implementation of the defined system.
-
DISTRIBUTION
-
5.1 Quality Control
-
5.2 Production
-
5.3 Engineering
DEFINITION(S) & ABBREVIATION(S)
-
6.1 Definitions
- 6.1.1 DG Set: Diesel Generator Set produces electrical power by consuming diesel. It works as alternate power back-up of the plant.
-
6.2 Abbreviations
-
6.2.1 B/C: Bus Coupler
-
6.2.2 ACB: Air Circuit Breaker
-
6.2.3 SOPs: Standard Operating Procedures
-
6.2.4 M/C: Machine
-
6.2.5 Amp: Ampere
-
PROCEDURE
-
7.1 Pre-Start Checking:
-
7.1.1 Clean the outer surfaces of the DG Set using cotton cloth.
-
7.1.2 Check the fuel (diesel) level using stick having a minimum marking level. It should be above the minimum level.
-
7.1.3 Check the coolant water level. It should be visible from the top of the radiator.
-
7.1.4 In the DG electrical panel, select the key to 'Run' mode. Check the battery voltage in the DG electrical panel. The value should show minimum 22 volt DC.
-
-
7.2 Start-up Procedure:
-
7.2.1 In the DG electrical panel, select the key to 'Run' mode.
-
7.2.2 In the Power Control Centre area, go to the DG Breaker panel. Select the switch to Auto mode.
-
7.2.3 In the Power Control Centre area, go to the B/C Breaker panel. Select the switch to DG-2.
-
7.2.4 In the Power Control Centre area, go to the DG Breaker panel. Pull the lever of the breaker on by moving it from right to left side.
-
7.2.5 Similarly, switch on the B/C Breaker.
-
-
7.3 Checks While Running:
-
7.3.1 Check the voltage in the display located in the DG electrical panel. LL (Line to Line) voltage should not be less than 220 volts.
-
7.3.2 Keep checking the fuel level every half an hour. The level should not be below the minimum level.
-
7.3.3 Every half an hour, keep checking the temperature in the temperature display located at the DG electrical panel. It should not be more than 80 °C.
-
7.3.4 Every half an hour, keep checking the oil pressure in the display located at the DG electrical panel. It should not be less than
-
-
2.5 kg/cm².
- 7.3.5 Every half an hour, keep checking the load (Amp) in the display located at the DG electrical panel. It should not be more than as per machine
-
7.4 Closing of DG Set:
-
7.4.1 In the Power Control Centre area, first switch off the breaker of B/C by pressing the 'Trip' push button.
-
7.4.2 In the Power Control Centre area, switch off the breaker of DG-2 by pressing the 'Trip' push button.
-
7.4.3 Wait for ten minutes for the DG Set to cool off.
-
7.4.4 In the Power Control Centre area, go to the DG Breaker panel. Select the switch to Manual mode.
-
7.4.5 In the DG electrical panel, select the key to 'Off' mode.
-
REVISION HISTORY
+----------------+----------------+----------------+----------------+----------------+----------------+ | Revision No. | 00 | Effective | | CC No. | | | | | Date | | | | +----------------+----------------+----------------+----------------+----------------+----------------+ | Details of revision: New SOP | +-----------------------------------------------------------------------------------------------------+